Brigade Valencia Electronic City: Phase 1 Sold Out

In brief

Brigade Valencia is a Brigade township near Electronic City; its Cielo phase has 662 flats, possession due 31 December 2027, and Phase 1 is sold out.

Developer: Brigade Enterprises Ltd

  • Project statusUnder Construction
  • Registered on12 Jan 2023

Facts verified Raaghav Valekar profile photoRaaghav Valekar22 min read

Video review

Brigade Valencia Review 2026: Not Really Electronic City?

In this video

Brigade Valencia review (2026): possession date, construction status, price, 2 BHK floor plan in 3D, location and the 220 kV power line. Independent research, no commission.

Watch on YouTube

Key takeaways

  • Brigade Valencia is Brigade Enterprises' township at Bommasandra, off Hosur Road, which Brigade markets as Electronic City.
  • Its first phase, registered as Cielo at Brigade Valencia, has 662 flats from 1 BHK to 4 BHK, with super built-up sizes of 586 to 2,276 sq ft in our facts.
  • Our recorded reference rate for Cielo is ₹11,350 per sq ft (reviewed 24 August 2026), and Brigade's project website says Phase 1 is sold out. Karnataka RERA lists possession on 31 December 2027.
  • Delta Electronics Bommasandra metro station is 2.0 km by road, and the second phase, Brillio, is a separate registration with a September 2029 date.

Project at a glance

City

Bangalore

Project type

Apartments

Project approved by

Local planning authority (plan APA/CC/207/2022-23), per the RERA record

Total Land Area

About 7.97 acres (3.47 lakh sq ft) for the Cielo phase in our factsBrigade gives 24 acres for the whole township

Address

Kithiganahalli and Banahalli, Bommasandra Industrial Area, off Hosur Road (marketed as Electronic City)

Total Units

662 units in the Cielo phase

No of Floors

2B+Stilt+G+22 in our factsthe RERA tower row lists 22 floors, 1 stilt level and 2 basements

No of Towers/Blocks

1 registered block: Cielo at Brigade Valencia

Nearest landmark

Bommasandra Industrial Area

Expected Launch Date

1 February 2023 (project start date in the RERA record)no separate public launch date in our facts

Developer Track Record

44 Karnataka RERA projects in our data with no recorded extension18 of them now show a later completion date than at registration43 RERA complaints listed across 19 projects (28 August 2026)

Possession Date

31 December 2027

Amenities

Clubhouse, Gymnasium / Fitness Center, Kids' Play Area, Outdoor Gym, Mini Theatre, Swimming Pool