By home count, Phase 3 is the largest of the three registrations. Nambiar EnsembleResidential Projects LLP registered Phase 1 on 10 January 2025 and Phase 2 on 20 August 2025. Phase 3 followed on 26 May 2026. Our Karnataka RERA data was last updated on 28 August 2026.
| Phase |
RERA approval |
Completion |
Homes |
Towers |
Floors |
| Phase 1 |
10 January 2025 |
26 January 2030 |
796 |
6 (Towers 1 to 6) |
32 to 33 |
| Phase 2 |
20 August 2025 |
31 August 2030 |
816 |
6 (Towers 7 to 12) |
34 |
| Phase 3 |
26 May 2026 |
29 February 2032 |
1,202 |
8 (Towers 13 to 20) |
36 to 38 |
Phase 3 completes about 18 months after Phase 2 and has the tallest towers of the three. Together the three registrations list 20 towers and 2,814 homes.
The builder's website (checked 20 October 2026) lists this RERA number for Phase 3. It describes 20+ acres with sports amenities, 85 percent open space and 4 units per floor. Four homes on each of 38 floors gives 152, which matches the RERA count for Towers 15 to 18. Larger land figures come from portals. HomeBazaar lists "20 Towers of 3B+G+39 Storey in 200 Acres" (checked 20 October 2026), and a promotional site says 100 acres. The 20 towers match the three RERA registrations added together. The land and the floor count do not match this registration, our approved figures give about 11.5 acres, and the RERA tower rows list 38 floors at most.
RERA registers the project under the same name we use. The builder's website trades as Nambiar Builders Pvt. Ltd., while RERA names the promoter as Nambiar EnsembleResidential Projects LLP. Our approved figures give the status as New Project Launch, with a project start date of 15 July 2026. RERA lists the status as Approved. The builder's status page shows photo updates for Phases 1 and 2 only, the latest dated 7 May 2026, and none for Phase 3.
RERA lists estimated construction windows. The frame runs from 18 August 2027 to 11 October 2029. Masonry runs from 15 September 2027 to 15 December 2028. Plastering runs from 15 December 2027 to 12 December 2029. Water, sanitary and electrical work runs from 14 January 2028 to 22 January 2031. Joinery runs to 25 December 2030, and flooring and tiles to 6 June 2031. These are RERA estimates dated 28 August 2026. They are not progress reports.
We found no independent resident review of Phase 3 on 20 October 2026. Web results for the name were mostly profile pages and promotional stubs. In our Karnataka RERA data, updated 28 August 2026, the registration record carries 2 complaints. Both name Phase 2 in the record. One concerns a refund after a cancellation with an amount deducted. The other concerns material deviations and the non-refund of stamp duty and a balance amount. We publish no dates, because the record's columns are misaligned. The record shows no outcome. A complaint is an allegation, not a finding.